The Tulalip Tribes and WSDOT entered an agreement wherein WSDOT provided for $50 million in funding for the 116th Street Interchange/88th Street NE Project and other Tulalip Reservation I-5 Interchange improvements in order to fulfill its prior commitments to the Tulalip Tribes during the construction of I-5 in the early 1970s.

Approximately $15 million of the original $50 million was obligated and used to fund completion of the 116th Street Interchange by a Tulalip Tribal NAOB (Native American Owned Business) Contractor.

On January 25, 2019, the Tulalip Tribes and the City of Marysville submitted a joint letter advising WSDOT of their joint commitment to use the remaining funds to construction improvements on both the 4th Street/State Route 528/I-5 Interchange and the 88th Street NE/I-5 Interchange.

The costs of improvements at the two interchanges are undetermined at this time as the alternative selection process has not yet been completed.

Schedule

The Tulalip Tribes and WSDOT entered an agreement wherein WSDOT provided for $50 million in funding for the 116th Street Interchange/88th Street NE Project and other Tulalip Reservation I-5 Interchange improvements in order to fulfill its prior commitments to the Tulalip Tribes during the construction of I-5 in the early 1970s.

Approximately $15 million of the original $50 million was obligated and used to fund completion of the 116th Street Interchange by a Tulalip Tribal NAOB (Native American Owned Business) Contractor.

On January 25, 2019, the Tulalip Tribes and the City of Marysville submitted a joint letter advising WSDOT of their joint commitment to use the remaining funds to construction improvements on both the 4th Street/State Route 528/I-5 Interchange and the 88th Street NE/I-5 Interchange.

The costs of improvements at the two interchanges are undetermined at this time as the alternative selection process has not yet been completed.

WSDOT Funding Allocation - $50 million

  • 116th Street NE Interchange Completion
  • 4th Street Interchange
  • 88th Street NE Interchange
  • $15M
  • $17M
  • $18M

WSDOT Funding Allocation - $50 million

  • 116th Street NE Interchange Completion
  • 4th Street Interchange
  • 88th Street NE Interchange
  • $15M
  • $17M
  • $18M